Tarouba stadium steel ‘condemned’
By Andre Bagoo Sunday, March 22 2009
THE STRUCTURAL steelwork on the $900 million Brian Lara Stadium project at Tarouba “is effectively condemned”, according to a report into the Udecott project prepared by Gerry McCaffrey, the construction expert hired by the Uff Commission of Inquiry whose future participation in the inquiry has now been cast in doubt.
According to McCaffrey’s initial report into the project dated February 20, the main contractor for the project, Hafeez Karamath Limited (HKL) ignored 300 “stop orders” for work on the project. McCaffrey concluded that issues of “quality control” and of the inability of Udecott to enforce the terms of the contract for the project have contributed to delays on the project.
“I am advised that HKL have received hundreds of stop-orders for defective work,” McCaffrey wrote. “For example, I am advised that HKL ignore stop-orders to the extent that, as at January 2009, the structural steelwork (which was progressed in the face of around 300 stop-orders) is effectively condemned.”
http://www.newsday.co.tt/news/0,97102.html